Does my building need ERRCS?

There is no single national answer. Whether your building needs coverage, and a system to provide it, depends on your state or city's rules and on the radio signal inside your building. Here is how to work it out.

Last verified Updated 9 sourcesChangelog

The four questions that decide it

  1. Where is the building? Your state law and your local fire department's rules set the triggers. Find yours on the requirements pages.
  2. New or existing? New buildings usually face the full rule. Existing buildings are covered by retrofit rules, which vary the most.
  3. How big, how tall, how deep? Most triggers use square footage, stories, high-rise status and below-grade areas.
  4. What is the signal inside? Even a covered building needs a system only if the measured signal falls short. Under the model code, coverage is judged against the public safety signal measured at the outside of the building (IFC 2021 510.1), and Florida says no system or assessment is required if the signal is inadequate at the exterior (F.S. 633.202(18)(e)).

The building checker walks through these questions for the jurisdictions we cover and cites the source for every answer.

How triggers compare

This table lists new-building triggers and existing-building rules as published in each document. Open the jurisdiction page for the full rule and its exceptions.

JurisdictionNew buildingsExisting buildingsSource
Florida (statewide)All buildings must meet the local minimum signal; exempt: 1-2 family and townhouses, under 12,000 sq ft with no underground areas, low-rise apartments and lodging with exterior exits, some wood-frame apartmentsExisting high-rises: permit by January 1, 2024, comply by January 1, 2025F.S. 633.202(18)
San Diego, CAAll high-rises; low-rise with 3+ stories, over 20,000 sq ft, or larger basements (test, then system if failed); R-3 exceptedHigh-rise without wired phone system: test, install within 3 years if failedSDFD guideline II
San Francisco, CAAll new buildings; test low-rise after construction; exempt: one story, 12,000 sq ft or less, no basementHigh-rise without wired phone system: test, install within 3 years if failed; change of occupancy triggers a testSFFD AB 2.01 Addendum G, I
Los Angeles, CAWhere signal is below code and: more than 3 stories, 50,000+ sq ft, basement 10,000+ sq ft, 2+ levels below grade, or 20,000+ sq ft with solar PV; R-3 exceptedSame conditions, when the fire alarm system is replacedLAFD Requirement #105
Houston, TXAll buildings except those with no basement, 3 stories or less and 50,000 sq ft or lessRemodels and lease buildouts must document complianceHouston CE-1350
Phoenix, AZBenchmark RF test decides; policy lists under 3 stories and under 12,000 sq ft as exemption criteriaSame policy covers existing buildings meeting PFC 1103.2Phoenix Explanatory Policy
Washington (statewide)All new buildings, based on exterior signalNon-R-3 buildings when a wired system fails or is replaced, or on a local timelineWAC 51-54A-0510, 1103.2
Seattle, WAHigh-rises; 50,000+ sq ft; basement 10,000+ sq ft; occupied floors 30+ ft below exit dischargeHigh-rise with no wired system or coverage must retrofitSFD CAM 5123

If your city is not listed

Ask your fire marshal three things: which fire code edition and amendments apply, whether they publish ERRCS technical criteria (the model code requires one, IFC 2021 510.4.2.2), and whether existing buildings have a retrofit deadline. We add a jurisdiction only after reading its own documents. New and updated pages are listed on our changelog.

If you already have a notice

Read what to do after a fire marshal notice. It covers deadlines, who to hire and what records to keep.

This is guidance, not engineering advice. Confirm with your fire marshal (AHJ).

Questions people ask

My building passed its last inspection. Can it still need ERRCS?

Yes. Retrofit rules for existing buildings can apply regardless of past inspections. Florida's statute, for example, set January 1, 2025 as the date existing high-rises had to comply (F.S. 633.202(18)(a)), and a fire marshal can require a signal assessment on a schedule the statute sets.

Is a small building ever required to have ERRCS?

It can be, mostly because of basements or a weak local signal. In Florida a building under 12,000 total gross square feet is exempt only if it has no underground areas (F.S. 633.202(18)(h)2). San Diego's guideline covers new buildings with a basement over 2,500 sq ft.

Does "required" mean I must install a BDA?

Not always. In most codes, required means the building must have adequate coverage. If a signal test shows the building already has it, no system is installed. The model code bases coverage on the signal measured outside the building (IFC 2021 510.1).

Sources

Primary documents we read for this page. Rules change; confirm with your fire marshal (AHJ).

  1. Florida Statutes 2026, section 633.202, subsection (18), The Florida SenateVerified October 25, 2026 · statute
  2. International Fire Code 2021, Section 510 (text as published by the City of Eaton), City of Eaton, reproducing the ICC International Fire CodeVerified October 25, 2026 · code
  3. San Diego Fire-Rescue ERRCS guideline (9/22/23), City of San DiegoVerified October 25, 2026 · ahj document
  4. Administrative Bulletin 2.01 (2025), Addendum G, San Francisco Fire DepartmentVerified October 25, 2026 · ahj document
  5. Requirement, Los Angeles Fire DepartmentVerified October 25, 2026 · ahj document
  6. Emergency Responder Communication Coverage (ERCC) Guideline, Form CE-1350 (revised July 2025), City of HoustonVerified October 25, 2026 · ahj document
  7. Client Assistance Memo 5123 (November 2024), Seattle Fire DepartmentVerified October 25, 2026 · ahj document
  8. Fire Prevention Section Explanatory Policy Manual 2026, Emergency Responder Radio Coverage, City of Phoenix Fire DepartmentVerified October 25, 2026 · ahj document
  9. WAC 51-54A-0510, Emergency responder communication coverage, Washington State LegislatureVerified October 25, 2026 · rule