Independent reference. Not a government website. Guidance, not engineering advice: confirm with your fire marshal.

California · city · ERRCS / BDA requirements

ERRCS and BDA requirements in San Diego, California

In San Diego every new high-rise needs an ERRCS. New low-rise buildings need a radio coverage test, and a system if they fail, when they have 3 or more stories above grade, more than 20,000 sq ft, or multiple stories below grade or a basement over 2,500 sq ft. Group R-3 is excepted. Existing high-rises without a wired fire department phone system must test and, if they fail, install a system within 3 years.

Last verified Updated Confidence medium2 sourcesChangelog

Guidance, not engineering advice. Rules on this page come from the documents listed under Sources. Confirm with San Diego Fire-Rescue Department, Community Risk Reduction Division before you design, permit or test a system.

Who must comply

State rules apply here too. See California statewide rules.

RuleEffectCitationSource
Group R-3 occupancies are excepted from the low-rise triggers. The city's technical bulletin describes R-3 as single-family homes, duplexes and townhomes.Not requiredSDFD ERRCS guideline II.A.2 (Exceptions); TB FIRE 5-1 I.1City of San Diego, San Diego Fire-Rescue Department
All new high-rise buildings must have an ERRCS. A wired phone-jack system is not allowed in place of it.Must meetSDFD ERRCS guideline II.A.1City of San Diego, San Diego Fire-Rescue Department
New low-rise buildings with 3 or more stories above grade plane must pass a radio coverage test after construction; if the test fails, an ERRCS must be installed.Must meetSDFD ERRCS guideline II.A.2.aCity of San Diego, San Diego Fire-Rescue Department
New buildings with more than 20,000 sq ft of total building area must pass a radio coverage test; if it fails, an ERRCS must be installed.Must meetSDFD ERRCS guideline II.A.2.bCity of San Diego, San Diego Fire-Rescue Department
New buildings with multiple stories below grade, or a basement over 2,500 sq ft, must pass a radio coverage test.AHJ may requireSDFD ERRCS guideline II.A.2.cCity of San Diego, San Diego Fire-Rescue Department
Existing high-rise buildings without a wired fire department phone-jack system must run a radio test. If it fails, an ERRCS must be installed within 3 years of the test date.AHJ may requireSDFD ERRCS guideline II.B.3City of San Diego, San Diego Fire-Rescue Department
Other existing buildings must comply when a previously required wired fire department phone system is removed, or when a building permit is needed for a change of use or occupancy (not required if an operational wired phone-jack system exists).NoteSDFD ERRCS guideline II.B.1-2City of San Diego, San Diego Fire-Rescue Department
TriggerPublished value
Minimum building size20,000 sq ft
Minimum stories3
Height triggerNot published; confirm with the fire marshal
Below-grade areasTrue
Building types namedNot published; confirm with the fire marshal
Existing buildings must retrofitYes
Compliance deadlineNot published; confirm with the fire marshal

The guideline is dated 9/22/23 and written for the 2022 California Fire Code. The older Technical Bulletin FIRE 5-1 (September 2021) lists different new-building exceptions; the 2023 guideline is the newer document. Confirm which applies to your permit with San Diego Fire-Rescue.

RequirementValue
Minimum downlink signal-95 dBm
Minimum uplink signalNot published; confirm with the fire marshal
Delivered audio quality (DAQ)3.4
Coverage, general areas95% of floor area
Coverage, critical areas99% of floor area
Critical areas namedExit stairs, Exit passageways, Elevator lobbies, Fire protection equipment rooms and control valve locations, Fire command centers
Public safety radio bands700 MHz public safety; 800 MHz public safety

Inbound signal must be at least -95 dBm throughout the coverage area with DAQ 3.4 in both directions. Maximum propagation delay is 15 microseconds. Signal boosters must be Class A and operate only on the frequencies the city assigns. Downlink levels may not exceed -75 dBm at or near the building's interior perimeter.

Testing

TestWhat the source saysSource
Acceptance testAcceptance testing must be done by a third-party qualified testing entity not employed by or related to the installer. San Diego Fire-Rescue reviews the report, inspects on site, and returns a stamped report that the contractor uploads to The Compliance Engine. Pass is -95 dBm in 95% of the test grid and 99% of critical areas.SDFD ERRCS guideline, Appendix C
Annual testThe owner must have the ERRCS inspected and tested every year and whenever structural changes affect it. The testing contractor submits the annual report through The Compliance Engine. Annual testing may be done by the installer's qualified tester or a third party.SDFD ERRCS guideline V.A and Appendix C
Five-year testNot published in the documents we read; confirm with the fire marshal.None found
Coverage assessment intervalNot published in the documents we read; confirm with the fire marshal.None found

Maintenance and monitoring

  • Keep the acceptance report, the annual test report from the last 12 months and the city's written Authorization to Operate available for inspection.
  • The owner pays to modify or expand the system if the FCC changes frequencies or adds new ones.
  • Non-public-safety amplifiers that interfere with the ERRCS must be corrected or removed.

Source: San Diego Fire-Rescue Community Risk Reduction Division, Emergency Responder Radio Coverage Systems guideline (dated 9/22/23)

Permit and inspection process

  1. Plan for the system early: the guideline recommends installing conduit during construction in case the post-construction test fails. SDFD ERRCS guideline II.A
  2. Submit ERRCS plans to San Diego Fire-Rescue plan review (Appendix B lists what the plans must show). SDFD ERRCS guideline III and Appendix B
  3. Get the City's approval before installing any amplifier that can operate on the City public safety 700/800 MHz frequencies. SDFD ERRCS guideline IV
  4. Third-party acceptance test, city inspection, stamped report uploaded to The Compliance Engine. SDFD ERRCS guideline, Appendix C

Codes and standards referenced

Code or standardEditionSource
California Fire Code2022 (named in the guideline)s1
NFPA 12212019s1
NFPA 722022s1
UL 2524 listing for system componentsNot published; confirm with the fire marshals1

Notes

Medium confidence: the guideline we read is dated September 2023 and cites the 2022 California Fire Code. Check for a newer edition before you design.

Questions people ask

Does a new three-story building in San Diego need an ERRCS?

It needs a radio coverage test after construction. If the test fails, an ERRCS must be installed (SDFD ERRCS guideline II.A.2.a). Group R-3 occupancies are excepted.

Where do annual ERRCS test reports go in San Diego?

The testing contractor uploads them to The Compliance Engine, without prior review by fire department staff (SDFD ERRCS guideline V.A).

Sources

Primary documents we read for this page. Rules change; confirm with your fire marshal (AHJ).

  1. San Diego Fire-Rescue Community Risk Reduction Division, Emergency Responder Radio Coverage Systems guideline (dated 9/22/23), City of San Diego, San Diego Fire-Rescue DepartmentVerified October 25, 2026 · ahj document
  2. Technical Bulletin FIRE 5-1, Emergency Responder Radio Coverage Systems (September 2021), City of San Diego Development Services DepartmentVerified October 25, 2026 · ahj document