Florida · city · ERRCS / BDA requirements

ERRCS and BDA requirements in Orlando, Florida

Orlando requires a radio signal survey for every new building under construction and accepts surveys on existing buildings. A building that fails needs a fire permit for a radio enhancement system. Buildings that proved coverage with a grid report must show it again every year.

Last verified Updated Confidence high5 sourcesChangelog

Guidance, not engineering advice. Rules on this page come from the documents listed under Sources. Confirm with Orlando Fire Department, Fire Marshal's Office before you design, permit or test a system.

Who must comply

State rules apply here too. See Florida statewide rules.

RuleEffectCitationSource
A new building under construction must have an emergency radio signal survey. Passing results are uploaded under the building permit; failing results require a fire permit.NoteOFD, new building survey pageCity of Orlando, Orlando Fire Department
Properties that submitted grid reports as proof of coverage must demonstrate minimum radio strength annually or when the AHJ asks.NoteOFD, existing building survey pageCity of Orlando, Orlando Fire Department
TriggerPublished value
Minimum building sizeNot published; confirm with the fire marshal
Minimum storiesNot published; confirm with the fire marshal
Height triggerNot published; confirm with the fire marshal
Below-grade areasNot published; confirm with the fire marshal
Building types namedNot published; confirm with the fire marshal
Existing buildings must retrofitNot published; confirm with the fire marshal
Compliance deadlineNot published; confirm with the fire marshal

Surveys are run by a communications specialist with an FCC GROL license, on a control channel approved by the Orlando Police Department.

RequirementValue
Minimum downlink signal-95 dBm
Minimum uplink signal-95 dBm
Delivered audio quality (DAQ)3.4
Coverage, general areas90% of floor area
Coverage, critical areas99% of floor area
Critical areas namedFire command centers, Fire pump rooms, Exit stairs, Exit passageways, Elevator lobbies, Standpipe cabinets, Sprinkler sectional valve locations
Public safety radio bandsNot published; confirm with the fire marshal

Inbound: at least -95 dBm with DAQ 3.4 throughout the coverage area. Outbound: at least -95 dBm at the donor site with DAQ 3.4. Isolation between the donor antenna and inside antennas is at least 20 dB above the booster gain. The city assigns the control channel for each test.

Testing

TestWhat the source saysSource
Acceptance testFor new buildings, passing survey results are uploaded under the building permit number for formal approval. Do not upload failed results; a failed survey needs a fire permit referencing the building permit.OFD, new building survey page
Annual testProperties that submitted grid reports as proof of coverage must demonstrate minimum radio strength annually or at the request of the AHJ.OFD, existing building survey page
Five-year testNot published in the local documents we found; confirm with the fire marshal.None found
Coverage assessment intervalSet by state law: the fire marshal may require an interior coverage assessment no more than once every 3 years for an existing high-rise or an existing building over 12,000 total gross square feet, and once every 5 years for other existing buildings, with exceptions for major alterations, reported radio failures and imminent threats.F.S. 633.202(18)(c)2

Permit and inspection process

  1. Request a control channel from the Orlando Police Department through the city's authorization form; it answers within 3 business days. Step 1
  2. Have an FCC GROL-licensed communications specialist run the survey: control channel frequency, analyzer type, downlink and uplink calculations, DAQ values and a grid report for every floor. Steps 2 and documentation list
  3. Existing building: submit the results with the authorization letter. The Fire Marshal's office emails direction within seven business days. Step 3 and after submission
  4. New building: upload passing results under the building permit; for failing results, apply for a fire permit (DAS/BDA) with an electrical permit application. New building page

Codes and standards referenced

Code or standardEditionSource
Florida Fire Prevention Code (NFPA 1 and NFPA 101, Florida editions), in force statewide8th edition (NFPA 1, Florida 2021 edition), effective December 31, 2023rule

Questions people ask

What signal does Orlando require inside a building?

At least -95 dBm inbound and outbound with delivered audio quality (DAQ) of 3.4, in 99% of critical areas and 90% of general areas.

Our existing building passed. Are we done?

No. Orlando requires properties that proved coverage with a grid report to demonstrate minimum radio strength again every year, or whenever the AHJ asks.

Who can run the survey?

A communications specialist holding an FCC GROL license, using a control channel the Orlando Police Department approves.

Sources

Primary documents we read for this page. Rules change; confirm with your fire marshal (AHJ).

  1. Florida Statutes 2026, section 633.202, subsection (18), The Florida SenateVerified October 25, 2026 · statute
  2. Florida Fire Prevention Code, 8th edition: Florida amendments to NFPA 1 (2021 edition), sections 11.10.2 and 11.10.2.1, Florida Division of State Fire MarshalVerified October 25, 2026 · code
  3. Rule 69A-60.003, F.A.C.: NFPA 1, the Fire Code, Florida 2021 edition, adopted (effective 12/31/2023), Florida Department of State, Florida Administrative CodeVerified October 25, 2026 · rule
  4. Submit an Emergency Radio Signal Survey on an Existing Building, City of Orlando, Orlando Fire DepartmentVerified October 25, 2026 · ahj page
  5. Submit an Emergency Radio Signal Survey for a New Building Under Construction, City of Orlando, Orlando Fire DepartmentVerified October 25, 2026 · ahj page